IIAR 7-2025: the written routine that keeps the system alive

Refrigeration Insights Series. Season 3: The IIAR standards, installment 7 of 10.

Every plant has procedures. Some are written, versioned and available at the workstation. Others live in the head of the most senior operator, and leave with him when he retires. The difference between the two scenarios is exactly what ANSI/IIAR 7-2025 regulates, another of the three IIAR standards that debuted a new edition this year.

What IIAR 7 is

Its purpose is to define the minimum requirements for operating procedures of closed-circuit ammonia refrigeration systems. It is aimed at those who develop, define or review operating procedures: plant managers, operations leads, consultants and service contractors.

The scope is clear: every closed-circuit ammonia system must comply with it. And like the rest of the family, it marks out its territory well: decommissioning is not its subject but IIAR 8's.

What a procedure must include

Chapter 4 defines the substantive requirements. Four ideas structure everything:

Operating limits. Each procedure is written against the system's limits: pressures, temperatures, levels. Operating means keeping the system within its envelope; the procedure exists so that envelope is explicit.

Customization. The standard requires procedures to belong to the real system, not generic ones. An SOP photocopied from another plant does not comply: every circuit, every room and every piece of equipment has its particularities, and the procedure must reflect them.

Safety and regulatory considerations. Procedures integrate the applicable safety requirements; they neither duplicate nor contradict them.

The complete operating life cycle

Chapter 6 lists the procedures that must exist. Read in order, they tell the system's entire life: initial startup, normal operation, temporary operation, normal shutdown, emergency shutdown, emergency operation, and startup after abnormal conditions such as power outages or emergency stops.

That last point deserves underlining: startup after a power outage is one of the highest-risk operating moments in an ammonia plant, and one of the procedures most often missing in practice. If your plant has nothing written on how to come back from a blackout, IIAR 7 is pointing you to your first task.

Procedures are maintained too

Chapter 5 brings the part that separates mature programs from improvised ones: versioning and availability. Procedures are versioned, reviewed and must be available to those who operate. A perfect procedure stored away in the manager's office does not fulfill its function; an old version circulating around the plant is an active risk.

Practical advice

Take the inventory against the chapter 6 list: seven families of procedures. For each one, three questions: does it exist in writing?, does it reflect this system and not a generic one?, is the current version available where the system is operated? With that grid of seven rows and three columns you have your plant's operational maturity diagnosis in an hour of work.

Next week we change perspective: IIAR 9 and its Addendum A, the standard designed for systems that already exist.

Source: ANSI/IIAR 7-2025, Operating Procedures for Closed-Circuit Ammonia Refrigeration Systems, International Institute of Ammonia Refrigeration. Thermomac is a corporate member of the IIAR.